HINDUSTAN ZINC LTD:- RD & SK MINES
- Mine production : 1000000 te
- Drives & X cuts : 6750 mtr
- Raising : 600 mtr
- Incline shaft (30 degree) : 456 mtr
- Ramp 1 in 8 : 1994 mtr
- Sump & other excavation : 25000 cum
- Rock bolting : 29250 nos
- Diamond drilling (u/g) : 5500 mtr
HINDUSTAN ZINC LTD:- ZAWAR MINES
Shaft (vertical) : 190 mtr
Shaft equipping : 363 mt
Drives & X cuts : 10200 mtr
Raising : 2500 mtr
Ramp 1 in 8 : 925 mtr
Sump & other excavation : 27000 cum
Rock bolting : 6000 nos
Diamond drilling (u/g) : 4000 mtr
M/s. Hindustan Zinc Limited
Sindesar Khurd Mines
Nature of work : Mine production and associated mine development works at SK Mines
W/o : HZL/RD/DE/SK/MI/07-08/839 dtd:27.08.07
Order value : 1570 Lakhs
Period of Execution : 24 Months
Work commencement : 05.08.07
M/s. Hindustan Zinc Limited
SINDESAR KHURD MINES
Development of 5.5mx4.5m Ramp at SK Mine Phase III
Work order : HZL/PROJ/CONT/SKM/EXPAN3/08/06
Order value : 1000 Lakhs
Work commencement : 05.08.08
period of completion : 12 months
M/s Hindustan Zinc Limited:
Zawar Group of Mines
Underground Mine development works at Mochia Mines
Work Order/Job No : 930322
Work order Value : 1244 Lakhs
Work commencement : 01.03.08
period of completion : 24 months